Documentation Index

Fetch the complete documentation index at: https://docs.paneco.energy/llms.txt

Use this file to discover all available pages before exploring further.

5 Installation

Prev Next

5.1. Installing Tools

Needed tools

Description

Network Cable Pliers (8P)

Used to tighten the connector of the AC cable

3mm flat-head screwdriver

Tighten the dry contact signal cable

Torque wrench (19mm)

Used to tighten AC cable nuts

Open end wrench (19mm)

Used to fix the connection nut

Hexagon wrench (5mm)

For battery PACK and PCS room ceiling bracket installation

Diagonal cutting pliers

Used to cut protection ring on fire solenoid valve

Electric hand drill

It is used with double head cross head for disassembly and installation of

equipment

Double head cross head

It is used with electric hand drill for disassembly and installation of

equipment

Multimeter

Used to measure power grid, battery voltage and frequency

Cutting machine

Cut the entry hole baffle

Phase sequence table

Test AC voltage and three-phase line phase sequence

5.2. Remove the Temporary baffle plate

Temporary protective measures must be installed in the PCS room during container transportation. Remove the temporary baffle after container installation. Baffles are located on three sides of the PCS room, as shown in Figure 5-1. Table 5-1 baffles' positions and numbers.

NOTICE

If the baffle plate is not removed, heat dissipation of PCS will be affected, resulting in overheating and device shutdown.

Figure 5-1 Temporary baffle position

Table 5-1 Baffle position and number

Symbol

Explain

1#

Container side C 1# baffle plate

2#

Container side A 2# baffle plate

3#

Container side D 3# baffle plate

Remove the screws from the baffle plate and remove the baffle plate, as shown in Figure 5-2.

Tool name

picture

Electric hand drill

Double head cross head

NOTICE

PCS protection grade is IP66, which can work completely in the open air environment.

Figure 5-2 Container appearance after the baffle plate is removed

After the baffle plate is removed, the exposed fixed holes must be filled with anti-corrosion materials to avoid affecting the service life of the system.

NOTICE

The screw holes fixing the baffle shall be treated with anti-corrosion.

Make sure that each fixing hole is filled with anticorrosive material to avoid direct exposure to air.

Figure 5-3 Corrosion protection of fixed holes

5.3. Energy storage system opens the door

In the transportation process of the energy storage system, all the door locks are added to prevent the door from being opened.

NOTICE

Do not open the door in bad weather such as rain, snow, lightning, sand and dust

Step1:

Open the emergency stop button box and take out the door lock key

STEP 1

Hold and pull down

STEP 2

Rotate it 90 degrees to the right

STEP 3

Open the emergency stop cabinet door

STEP 4

Cut off the binding and take out the key

Step2: Open the door of the electrical room

Step3:

Open the battery room door

NOTEC

Container door opening instructions

5.4. PCS room ceiling bracket installation

Figure 5-4 PCS room ceiling location

Table 5-2 Ceiling location and number

Symbol

Explain

4#

PCS Room 4# Ceiling

5#

PCS Room 5# Ceiling

CAUTION

The top height of the container is 2.6m, and the disassembly of the PCS room ceiling belongs to the high work. Please comply with the relevant regulations on the precautions for high work when disassembling.

Tool name

picture

Hexagon wrench (5mm)

After you remove the ceiling, you'll see a protective net

Figure 5-5 PCS room protective net

5.5. Grounding the System

Containers must be securely grounded to ensure personal safety. The container shell provides two ground points. The ground points are arranged diagonally at the bottom of the container, as shown in Figure 5-9. After the container is secured to the base, weld the external ground flat steel to the ground point of the container shell, and take anti-corrosion measures according to the electrical standards.

Figure 5-6 Container ground point

When using the following two grounding methods, ensure that the grounding resistance is less than 10Ω.

Figure 5-7 Container flat iron grounding

To install the system grounding pole, refer to the local national or local electrical standards.

5.6. Installing Battery Pack

NOTE

Part of the battery PACK may be removed during shipping and will need to be reinstalled when the device arrives at the installation site.

DANGER

Each battery PACK weighs about 111.5kG. Use professional loading and unloading tools to carry it.

NOTE

Please follow the operation specifications for special equipment during device handling.

Do not scratch the surface of the device or damage the components when moving the device. When using a forklift, the forklift must be in the middle position to avoid tipping over. Before moving, please fasten the equipment to the forklift with ropes; When moving, a special person should take care of it.

Move equipment carefully to avoid collisions or falls.

Transport the battery PACK to the container, remove the packaging, and check the appearance of the device.

Figure 5-8 Battery PACK transport mode

NOTICE

It is prohibited to install in bad weather such as rain, snow, thunder, and dust.

Description of the battery string type and label

Battery PACK Size (W×D×H) (480×750×242mm)

Battery PACK Type A

Battery PACK Type B

Battery PACK Type A: XBP1, XBP2, XBP3, XBP4, XBP5, XBP6, XBP7, XBP8, XBP17, XBP18, XBP19,

XBP20, XBP21, XBP22, XBP23, XBP24;

Battery PACK Type B: XBP9, XBP10, XBP11, XBP12, XBP13, XBP14, XBP15, XBP16;

Figure 5-9 Battery PACK type

Figure 5-10 Battery PACK label description

Example:

1BP1 ------ 1#The first battery in the battery string(1BC) X---1 Y-----1

2BP1 ------ 2#The first battery in the battery string(2BC) X---2 Y-----1

2BP24------ 2#The 24th battery pack in the battery string(2BC) X---2 Y-----24

Cabinet installation rules

Install the battery string according to the definition on the preceding battery string label

Tool name

picture

Hexagon wrench (5mm)

Figure 5-11 Battery PACK installation position

5.7. Battery cluster cable installation

NOTE

The battery string cable has been removed during transportation. Install it again after the device arrives at the installation site.

All cables are stored in a carton under battery cluster 2# (2BC) in the battery room.

Take out the battery cluster cables in the carton

Figure 5-12 Location of carton with cargo

The DC cable ends are fixed

Figure 5-13 Fixed end of DC cable

NOTE

To remove the end, pull it out and hold down the Lock button in the figure. When you plug in the terminal, you can hear a popping sound, which means it has been plugged in tightly and the connection is reliable.

NOTICE

When the joint is inserted tightly, there will be breaking sound, if the joint is not inserted tightly, there will be equipment damage!

The communication cable must be secured during installation. If you skip this step, the system may fail to communicate. The system communication interface is defined in section 3.1.1Battery pack.

Tool name

picture

3mm flat-head screwdriver

Figure 5-14 Communication line fixed instructions

Figure 5-15 Communication line connection connection

5.8. Installing the Spare Battery of the Fire Controller

NOTE

The battery of the fire controller has been removed during transportation. Reinstall the battery after the device arrives at the installation site.

Batteries are stored in a carton under battery cluster 2# (2BC) in battery room.

STEP 1

Unpack and take out the battery

Figure 5-16 Spare batteries of the fire controller

STEP 2:Open the door of the fire controller

Figure 5-17 Fire controller matching key

STEP 3:Install the battery of the fire controller

Figure 5-18 Battery polarity specification

DANGER

When connecting, pay attention to the positive and negative battery terminals.

Figure 5-19 Installation location of backup battery

Grey cable--------battery series connection

Red cable------Battery positive connection

Black cable-------Battery negative connection

Step1: Connect two batteries in series

Figure 5-20 Battery series connection Step2: Install the series connected battery onto the fire controller

5.9. Installation of fire solenoid valve

STEP 1:Cut the protection ring

Tool name

picture

Diagonal cutting pliers

Cut the blue protective ring

Figure 5-21 Fire solenoid valve

STEP 2:Remove the gas cylinder cover

Figure 5-22 Remove the fire cylinder cover

STEP 3:Install the fire solenoid valve

Figure 5-23 Install the fire solenoid valve

5.10. Fire hammer installation

NOTE

The fire hammer has been removed during transportation and needs to be reinstalled when the equipment arrives at the installation site.

The fire hammer is stored in the carton under battery cluster 2# (2BC) in the battery room. Please open the carton and take it out.

STEP 1:Take out the fire hammer from the carton

STEP 2:Install the fire hammer

Figure 5-24 Fire hammer installation